Construction Update
July 2019

“The past month has gone well at the Neo Apartments site with piling works on-going around the perimeter of the building and minor earthworks commenced. Over the next month we plan to commence bulk excavation along with starting the concrete works around the exterior capping beam. We are also aiming to get the tower crane erected at the start of September which will allow logistics of materials around site to become easier.”

— James Sutherland, CMP Construction